Municipal Infrastructure Report
The Municipal Infrastructure Report (MIR) encompasses
a study of the major elements of the Towns infrastructure
under the responsibility of the Board of Public Works
(BPW). These include: North Attleboroughs Roads,
Bridges, Sidewalks, Wastewater Treatment Facility, Sewer
Collection and Water Distribution Systems, Pump Stations,
Water Treatment Facilities, Drainage structures, and
DPW Vehicles and Equipment.
The municipal infrastructure typically represents one
of the largest investments for a community. North Attleborough's
infrastructure replacement value has been conservatively
estimated at over $225,000,000. Consequently, it is
very important that the Town's infrastructure continue
to be managed efficiently and effectively.
The benefits of a comprehensive municipal infrastructure
plan include: a better understanding of the total infrastructure
needs within the community, improved management practices
and better decision making; increased ability to determine
the overall infrastructure replacement/repair costs
thus allowing officials to seek the most appropriate
funding options from local, state and federal sources;
and less time and effort to update annual operating
and capital budgets.
The MIR was accomplished by using the following approach:
Physical inventory of the infrastructure elements
Analysis of the condition, age, and repair/replacement
needs
Computerization of the data associated with this information
Determination of the cost to repair/replace
Prioritization of the infrastructure categories and
individual projects with respect to when they should
be replaced/repaired
FUNDING:
The Town of North Attleborough identifies and prioritizes
its anticipated capital expenditures each year in a
five year Capital Improvement Program (CIP). The CIP
has two major components: the Capital Budget, which
is the first year of the program; and the Capital Plan,
which is represented by the remaining four years.
The BPW's future capital requests average over $7.5
million annually, or nearly $38 million for the five
year program. In the recent past, however, there has
been approximately $600,000 to $900,000 spent annually
for Capital Improvement Projects. This allotment represents
approximately 13% of the requested amount. The gap between
these two figures is substantial and has caused replacement/repair
schedules to be lengthened. Presently, the replacement/repair
for infrastructure under the jurisdiction of the BPW
is funded through various methods: Taxation, Water Enterprise
Fund, Chapter 90, and State Revolving Fund grants (SRF).
For the past several years, the Town of North Attleborough
has received approximately $550,000 annually for road-
related projects through Chapter 90. Obviously, in order
to complete the requested capital projects, additional
funding is needed.
CONCLUSION:
This document was created to identify, evaluate and
prioritize all of the BPW capital needs for the immediate
future. It has been noted that there have not been adequate
funds allocated for Capital Improvement Projects in
the recent past. Efforts to combat this problem, however,
are currently being investigated through two Adhoc committees
sponsored by the Board of Selectman.
The information contained in the MIR will be updated
annually to reflect changing priorities, new technologies,
future Federal and State regulations, and public input.
Additionally, future items may include a comprehensive
look at intersection improvements, new federal regulations
such as NPDES Stormwater Phase II, and an expanded new
sidewalk program. The MIR will be shared with other
utilities in the Town of North Attleborough such as the
North Attleborough Gas Company, North Attleborough Electric
Department, etc. in an effort to coordinate replacement/repair
schedules thereby minimizing disruption to the public.
This document will also be provided to the Town's political
representatives in an effort to seek their support for
additional funding for these important projects. Additionally,
it is planned to hold a public hearing in the very near
future to allow for citizen input on this matter.
The municipal infrastructure is vitally important to
the social, economic and environmental well being of
our community. While infrastructure repair and replacement
can be costly, it should be viewed as an investment
in the future of North Attleboro.
Table of Contents for Municipal Infrastructure:
Bridges
There are 18 bridges under the jurisdiction
of the Department of Public Works within the Town of
North Attleborough. Some of the bridges have recently been
reconstructed such as the Towne Street Bridge, the Mount Hope
Street Bridge and the Fisher Street
Bridge.
During 1999, the Board of Public Works
recently contracted with Beta Engineering to complete
a comprehensive evaluation of the 18 bridges. This evaluation
included:
- Field Inspection for each of the 18 bridges
- Update of the Load Rating
- Repair/Replacement cost budgeting (View
in Current Window OR View
in New Window)
- Prioritize repair/replacement schedule
- Estimated life expectancy for each structure
- Evaluation Report
- Summary of potential funding sources
The evaluation indicated that one bridge,
Huntsbridge Road Bridge, is in poor condition and is
on the State of Massachusetts "Red List".
A Red List designation means the State has identified
the bridge as being deficient and in need of extensive
repair or replacement. Bridges on the Red List are inspected
twice per year, and could require action at anytime.
Beta Engineering is currently designing temporary repairs
to this bridge. This will keep the bridge useable for
the near future until State funding is received for
complete rehabilitation.
Bridge Prioritization:
The eighteen structures that were evaluated
as part of this program have been prioritized I through
18, with I being of highest priority. Below is a
summary of the recommendations for each structure.
In general, the first thirteen structures were found
to have varying levels of structural and safety deficiencies.
The remaining five structures have either very minor
deficiencies or are currently under reconstruction and
therefore require little attention at the present time.
Priority I - Huntsbridge Road over
the Abbotts Run River
Huntsbridge Road Bridge (Br. No. N-16-05)
is a stone arch structure spanning the Abbotts Run River.
This structure is in very poor condition with numerous
structural and safety deficiencies noted. This bridge
currently has an AASHTO sufficiency rating of 17.0 and
a five-ton posted weight limit. The Southeast spandrel
wall requires immediate repair to prevent structural
failure. This bridge has been accepted into the Massachusetts
Highway Department's Footprint Bridge Program. Under
this program the entire bridge will be scheduled for
replacement and funded by the Massachusetts Highway
Department.
Priority 2 - Fisher Street over
the Ten Mile River
Fisher Street Bridge (Br. No. N-16-17)
is a steel stringer structure spanning the Ten Mile
River. This structure is in very poor condition with
substantial section loss on the steel stringers with
severe deterioration of the concrete deck. This bridge
is currently posted for 8 Tons. Construction drawings
and Design Specifications for structure rehabilitation
have been prepared by BETA.
Priority 3 - Chestnut Street over
the Ten Mile River
Chestnut Street Bridge (Br. No. N-16-14)
is a steel stringer structure spanning the Ten Mile
River. This structure is in very poor condition with
substantial section loss on the steel stringers with
severe deterioration of the concrete deck. This bridge
is currently posted for 10 Tons. BETA recommends a complete
replacement of the existing superstructure and rehabilitation
of the existing concrete substructure.
Priority 4 - Mendon Road over the
Abbotts Run River
Mendon Road Bridge (Br. No. N- 16-04)
is a steel stringer structure spanning the Abbotts Run
River. This structure is in marginal condition with
several noted deficiencies. There are many voids (up
to 4'-6" deep) in the stone masonry abutments.
Sidewalk, Safety Curb, and Endposts; exhibit a high
level of concrete deterioration. The Town of North Attleborough
is considering realignment of Mendon Road. This bridge
is currently not posted. This bridge may be eligible
for the Massachusetts Highway Department's Footprint
Bridge Program.
Priority 5 - Cushman Road over the
Abbotts Run River
Cushman Road Bridge (Br. No. N- 16-03)
is a prestressed plank structure spanning the Abbotts
Run River. This structure is in fair condition with
several noted deficiencies. The guardrail is in very
poor condition. The narrow roadway width and poor alignment
impose a significant hazard to pedestrians and motorists.
BETA recommends complete replacement of the bridge structure
since it is functionally obsolete with respect to roadway
width and bridge railings. Improved roadway alignment,
sidewalks, utility supports and historical considerations
should be integrated into the design of the new structure.
This bridge is currently not posted. This bridge may
be eligible for the Massachusetts Highway Department's
Footprint Bridge Program
Priority 6 - Broadway over Scotts
Brook
Broadway Bridge (Br. No. N-16-21) is
a cast-in-place deck slab structure on rubble stone
masonry abutments spanning the Ten Mile River. This
structure is in poor to fair condition with several
deficiencies noted. There are several voids (up to 3'
deep) and dislodgment of some stones in abutments. The
East side of the North abutment is bulging and in need
of repair. This bridge is currently not posted. Based
on our field observations the structure appears to be
performing adequately and meets the minimum statutory
AASHTO loading requirements. BETA recommends that the
Town schedule this the structure for repairs and rehabilitation.
Priority 7 - Old Post Road over
the Seven Mile River
Old Post Road Bridges (Br. No. N-16-02)
are granite slab structures spanning the Seven Mile
River. These structures are in fair condition with some
deficiencies noted. Three slabs in the South bridge
have collapsed and railroad tracks are supporting a
slab in the North bridge. This bridge is currently posted
for 12 Tons. Based on our field observations the structure
does not appear to be performing adequately. Construction
drawings and Design Specifications for structure replacement
have been prepared by BETA.
Priority 8 - Broad Street over
the Ten Mile River (North Bridge) Broad Street Bridge
(Br. No. N- 16-20) is a granite slab structure spanning
the Ten Mile River. This structure is in fair condition
with several deficiencies noted. There are numerous
areas where stones are either missing or displaced (up
to V) in the loose laid stone masonry abutments. This
bridge is currently posted for 12 Tons. Based on our
field observations the structure does not appear to
be performing adequately. BETA recommends a complete
replacement of the structure.
Priority 9 - Freeman Street over
the Ten Mile River
Freeman Street Bridge (Br. No. N-16-09)
is a cast-in-place T-Beam superstructure with concrete
abutments spanning the Ten Mile River. This structure
is in fair condition with several deficiencies noted.
There are many spalls with exposed rebar and hollow
sounding areas. This bridge is currently not posted.
Based on our field observations the structure appears
to be performing adequately and meets the minimum statutory
AASHTO loading requirements. BETA recommends that the
Town schedule this the structure for repairs and rehabilitation.
Priority 10 - Avery Street over
Scotts Brook
Avery Street Bridge (Br. No. N- 16-22)
is a cast-in-place deck structure spanning across Scotts
Brook. This structure is in fair condition with minor
deficiencies noted. This bridge is currently not posted.
Based on our field observations the structure appears
to be performing adequately and meets the minimum statutory
AASHTO loading requirements. BETA recommends that the
Town schedule this the structure for repairs and rehabilitation.
Priority I I - Mansfield Road over
the Bungay River
Mansfield Road (Br. No. N-16-07) consists
of three concrete pipes and one cast-in-place concrete
box culvert structure spanning the Bungay River. This
structure is in good condition with minor deficiencies
noted. This structure is currently not posted. Based
on our field observations the structure appears to be
performing adequately and meets the minimum statutory
AASHTO loading requirements. BETA recommends that the
Town schedule this the structure for repairs and rehabilitation.
Priority 12 - Draper Avenue over
the Seven Mile River
Draper Avenue Bridge (Br. No. N-16-01)
is a cast-in-place concrete structure spanning the Seven
Mile River. This structure is in fair condition with
minor deficiencies noted. This structure is currently
not posted. Based on our field observations the structure
appears to be performing adequately and meets the minimum
statutory AASHTO loading requirements. BETA recommends
that the Town schedule this the structure for repairs
and rehabilitation. The following items should be addressed
to extend the life of the structure and improve safety:
• Replace approach guardrail.
• Repair spall on South guardrail.
• General maintenance including removal
of debris.
Priority 13 - Broad Street over
the Ten Mile River (South Bridge)
Broad Street Bridge (Br. No. N-16-19)
is a granite slab structure spanning across the Ten
Mile River. This bridge appears to be abandoned. Heavy
overgrowth at the opening, and limited visibility hampered
the inspection of the underside of the structure. This
bridge is currently posted for 12 Tons. Based on our
field observations the structure does not appear to
be performing adequately. The Town should strictly enforce
the posted load rating. Since the structure does not
serve any purpose, BETA recommends that the Town schedule
its permanent removal.
Priority 14 - Cedar Road over the
Ten Mile River
Cedar Road Bridge (Br. No. N-16-23)
is a three span concrete box culvert structure spanning
across the Ten Mile River. This bridge is in good condition
with minor deficiencies noted. This bridge is currently
not posted. Based on our field observations the structure
appears to be performing adequately and meets the minimum
statutory AASHTO loading requirements. BETA recommends
that the Town schedule this the structure for repairs
and rehabilitation. The following items should be addressed
to extend the life of the structure and improve safety:
• Repair of concrete sonatube caps
on approaches.
• General maintenance including removal
of debris.
Priority 15 - Orne Street over the
Ten Mile River
Orne Street Bridge (Br. No. N-16-'16)
is a prestressed concrete structure spanning the Ten
Mile River. This bridge is in good condition with minor
deficiencies noted. This bridge is currently not posted.
Based on our field observations the structure appears
to be performing adequately and meets the minimum statutory
AASHTO loading requirements. The following items should
be addressed to extend the life of the structure and
improve safety:
• Repair of the control joint located
at the Northeast backside of the sidewalk.
• Repair of scoured area located
at West Abutment adjacent to drain pipe.
• General maintenance including removal
of debris.
Priority 16 - Paine Road over the
Abbotts Run River
Paine Road Bridge (Br. No. N-16-06)
is a cast-in-place concrete box structure spanning the
Abbotts Run River. This bridge is in good condition
with minor deficiencies noted. This bridge is currently
not posted. Based on our field observations the structure
appears to be performing adequately and meets the minimum
statutory AASHTO loading requirements. The following
items should be addressed to extend the life of the
structure and improve safety:
- General maintenance including removal of vegetation
should be performed.
Priority 17 - Towne Street over
the Ten Mile River
Towne Street Bridge (Br. No. N- 16-11)
is a dual precast structure spanning across the Ten
Mile River. This bridge, constructed in 1995, is in
excellent condition with minor deficiencies noted. This
bridge is currently not posted. Based on our field observations
the structure appears to be performing adequately and
meets the minimum statutory AASHTO loading requirements.
The following items should be addressed to extend the
life of the structure and improve safety:
- Tighten/replace of nuts/bolts on guardrail.
Priority 18 - Mount Hope Street
over the Ten Mile River
Mount Hope Street Bridge (Br. No. N-16-12)
is currently under construction by the Massachusetts
Highway Department. This bridge will be constructed
of 12" deep precast prestressed butted beams. This
structure will span across the Ten Mile River. The completion
date for construction is expected to be early winter
or late fall of 1999.
FLEET REPLACEMENT PROGRAM
Keeping the Town's infrastructure in good condition
requires that vehicles and equipment used for infrastructure
maintenance also be kept in good working order. The
challenge of maintaining vehicles is second only to
maintaining the infrastructure itself. Maintaining vehicles
in proper working order reduces downtime, optimizes
maintenance intervals, provides safer equipment, and
lowers parts costs. All of which, in turn, increase
work force productivity. Ultimately, regardless of how
well maintained a vehicle is, it will need to be replaced.
A replacement schedule for all vehicles/equipment in
the Department of Public Works has been completed. The
replacement schedule is based upon mileage/hours and/or
age of the vehicle. These parameters correlate well
with replacement age since they relate to the concept
of increasing operational and maintenance (O&M)
costs as vehicles age. The decision to replace a vehicle
versus repair is normally made when the cost to repair/maintain
a vehicle begins to exceed the operating cost of a new
vehicle.
Staff conducted a review of the operating cost for
each class of vehicles (e.g. one ton truck, pickup truck,
vans, 6 wheel dump truck, etc.) to determine an approximate
replacement schedule based on the previously mentioned
parameters. The Chief Mechanic keeps information on
basic repair costs and mileage for each vehicle in a
paper-based format. From this information, staff obtained
some basic cost per mile information. There are future
plans to purchase a fleet management software program
to allow for quick analysis of specific O & M costs
for each vehicle/equipment used by DPW.
Based on the analysis work done to date, the following
general replacement schedule is recommended:
| Type of Vehicle |
Replacement Cycle |
| Dump Trucks
|
12 Yrs. / 75,000 Miles |
| Pickup trucks (3/4, 1/2, 1 ton)
|
10 Yrs. / 60,000 Miles |
| Utility vehicles
|
7 Yrs. / 80,000 Miles |
| Vans |
8 Yrs. / 80,000 Miles |
Adherence to this replacement schedule will ensure
that vehicles and equipment are replaced on an appropriate
basis to minimize high operating costs and enhance proper
functioning equipment which will allow the DPW to continue
to deliver high quality customer services. As a vehicle
reaches its recommended replacement year, staff thoroughly
reviews its condition to determine if immediate replacement
is warranted or whether it can be retained for another
year.
Annual Maintenance of Roads
Strategy:
There are 116.01 miles of roads in the community
that require "Annual Maintenance" work. As
asphalt constructed roads age, the petroleum products
in their surfaces evaporate, causing roads to become
brittle, disintegrate and break up. The pavement will
continue to deteriorate until it fails and must be reconstructed.
An increased repair effort is required to keep passable
roads that have exceeded their useful pavement life.
The average cost for annual maintenance of roads is
$42,000 per mile while for reconstruction it
is $295,000 per mile. It is obviously less costly
for the Town to keep its roads from slipping into the
more expensive road reconstruction category. Thus, the
preferred method for road maintenance is to conduct
"annual maintenance" of roads versus reconstruction.
The strategy of the Department is to expend maintenance
repair funds on the roadways with a PCI rating between
61-92. This would represent the present funding provided
annually by the Town ($100,000.00) and all Chapter 90
funds provided annually by the State to North Attleboro
($550,000.00).
By adopting this policy the Department will be maintaining
89 % of the roadways that require varying maintenance
work to keep them out of the reconstruction category
which is the most costly. If money were expended on
roadways in the reconstruction category (PCI = 0-61)
fewer roads would be maintained and more roads would
fall into the reconstruction category thus increasing
the required funding in the future.
NEW SIDEWALKS
Sidewalks are extremely important to the community
as they provide a safe passageway for pedestrians such
as school children, walkers/joggers, etc. As such, there
should be an ongoing program to identify areas for new
sidewalks.
Over the next year, DPW staff will develop a "ratings"
matrix to assist in planning for additional new sidewalks
throughout the community. Additionally, the School Department
is developing a listing of sites for potential new sidewalks
based on the walking habits of children as they go to
and from school. Funding for these new sidewalks may
be available through Chapter 70 funds. The new sidewalk
program reflects an annual amount of $50,000 for installation
of new sidewalks.
Sidewalks in the Town of North Attleborough are constructed
of two different kinds of sidewalk materials; concrete
and asphalt. To ensure uniform appearance of the sidewalks
throughout the community, sidewalk materials will be
specified as per the Planning Board Rules and Regulations
Governing Subdivision of Land. An excerpt regarding
the rules and regulations for sidewalks is included
in the next section of the MIR.
Town Bylaw relating to sidewalks
The following Town bylaw refers to the betterment process
for new sidewalks.
Article XVII states " that the laying of curbstone
and installation of sidewalks shall be exempt from assessment
of betterments, unless an assessment is specified in
an article for the project approved by Town Meeting
vote. The abutting property owners shall be assessed
a sum not to exceed one half of the cost thereof."
Gravel Roads
In 1997 Vanasse Hangen Brustlin Engineering,
Inc. (VHB) Inc. completed a comprehensive study of North
Attleboro roads and sidewalks. The data from this study
was entered into a computerized roadway management software
program. This software allowed the data from the gravel
road inventory to be categorized and rated in terms
of its condition at the time of the inventory work.
However, the condition of gravel roads can change considerably
over a short period of time due to heavy amounts of
rain and other environmental conditions. Thus the gravel
condition index is to be used as a guide rather than
a strict prioritized listing.
There are over 5.4 miles of
gravel roads (View in
Current Window OR View
in New Window) in the community. Before a road can
be accepted and improved, there are a number of questions
that must be answered. They include:
- Is the gravel road that is being considered open
to the public or private?
- Is the road legally acceptable? (For example, the
road may simply be an easement)
- Are there over 50% of the abutters that have agreed
to participate in the acceptance and paving process?
- Are there public safety issues to be considered
with regards to whether the road should be accepted
and paved?
- Are there maintenance issues associated with the
gravel roads that would make it more/less desirable
for the Town to accept and pave it?
Town Bylaws related to gravel roads
There are two town bylaws that address
private ways. They are:
Article XI, Section 11 states
" The Board of Public Works will grade and patch
but not install drainage, on private ways that the Board
determines, with the approval of the Board of Selectmen,
require such repairs by public necessity, provided more
than one-half of the abutters, based on lots frontage,
on such private ways request such repairs and such private
ways have been open to use for over five (5) years.
No betterments will be assessed. The Town shall not
be liable for any such repair work done on private ways."
Article XVII, Section 4
states " Building of roads on accepted ways
of the Town shall be done under the Betterment Act with
the abutting property owners being assessed a sum not
to exceed one half of the cost thereof."
Policy for acceptance of roads
As there are a number of questions
to be addressed before the Town accepts gravel roads,
there must either be a petition from over one half of
the abutting property owners or a request from a Town
official before any action is taken in this area. If
the BPW decides to accept the road, it must be brought
before Town meeting where a majority vote is required.
If there is bonding associated with the request than
the vote is 2/3. The abutting property owners may be
assessed a sum not to exceed one half of the cost thereof.
The road(s) being accepted must be placed in the Town's
annual Capital Improvement Plan before it can be paved.
Improvements needed to the gravel roads
such as pavement, drainage, curbing, and/or sidewalks
shall be up to the discretion of the Board of Public
Works. The inventory of 5.4 miles of gravel roads in
Town is listed on the following page.

Infiltration and Inflow
Background:
Infiltration and Inflow (I/I) are extraneous quantities
of water, which enter the sanitary sewer collection
system and reduce the capacity of the system to transport
sanitary sewage to the Wastewater Treatment Facility.
Infiltration is groundwater that leaks into the sanitary
sewerage system through pipe joints and defects.
Inflow refers to storm water that enters sewers through
catch basins, sump pumps, down spouts, basement drains
and defective manholes.
Over the past several years, there have been three Inflow and Infiltration
studies, which have successfully located sources of
infiltration and inflow.
- 1987 - I/I Analysis
- 1989 - Sewer System Evaluation Survey (SSES)
- 1991 - Television Inspection report
The studies showed that infiltration was widespread
throughout the sewer collection system, with the worst
areas located north and west of Washington Street, and
also in the Falls area of Town near Coral Lake and Commonwealth
Avenue. However, the data showed that a lot of the inflow
in North Attleborough originates in four mini systems comprising
almost 60,000 linear feet of sewer pipe.
Infiltration and Inflow
Remediation Strategy:
The studies produced
a plan which divided the town into 17 smaller areas
called "mini systems" to determine
the severity of the I/I in different sections of town.
Each mini system was defined by a key manhole, through
which all of the flow from the mini system passes. A
total of 16 key manholes and mini systems were developed
to isolate the flow in North Attleborough. A 17th key
manhole and mini system was developed to separate Plainville's
flow from North Attleborough's. These mini systems were
then evaluated during low flow periods and prioritized
to determine the most cost effective and beneficial
areas to spend rehabilitation money.
The next phase of this project was to evaluate all
the sewer lines in each mini-system according to their
priority. This evaluation is completed utilizing a digital
camera and television inspection technology. A camera
travels through the pipes and records any and all defects.
Once this inspection determines the deficiencies, a
repair strategy is designed, and construction estimates
are prepared.
Different repair strategies are used depending on the
deficiencies found. Some potential repairs are:
- Complete sewer replacement
- Sewer pipe lining to seal all cracks or leaks
- Manhole rehabilitation and sealing
- Replacement of sections of sewer pipes
- Testing and sealing to repair poor joints
- Service connection replacement
- Root control

WASTEWATER TREATMENT FACILITY
History
Construction of North Attleboroughs original
sewer system began over 90 years ago. Since that time,
the system has been periodically expanded to accommodate
additional residential and industrial users. In 1909,
F.A. Barbour designed the Towns first wastewater
treatment facility (WWTF), which consisted of settling
tanks, a dosing tank, and intermittent sand filter beds.
In 1948, major improvements to the treatment facilities
were added, which included a primary clarifier, trickling
filter, secondary clarifier, and reuse of the sand filter
beds. A chlorine contact facility was added in 1959.
The effluent from the treatment facility discharges
into the Ten-Mile River, an interstate stream that also
serves as a source of public water supply in Rhode Island.
By the early 1960s, the facility could no longer
properly handle the Towns growing sewage flows.
Over loading of the WWTF various components caused unsatisfactory
wastewater treatment and environmental problems. Consequently,
in 1964, North Attleborough commissioned Whitman &
Howard, Inc., to evaluate its existing water pollution
control facilities and develop a long range, comprehensive
pollution control program. The resultant report recommended
increasing the capacity and efficiency of this facility,
specifically by constructing a secondary treatment facility,
which would incorporate some segments of the existing
plant and by rehabilitating the sand filter beds to
insure more efficient operation and improved treatment.
However, because effluent from the North Attleborough's
treatment facility significantly affected the water
quality of the Ten-Mile River, a higher level of treatment
was mandated in 1969 by the Massachusetts Water Resources
Commission, Division of Water Pollution Control.
The Federal Water Pollution Control Act Amendments
of 1972 established new federal guidelines and regulations
for sewage treatment projects. As a result, the Town
was required to satisfy many new regulatory requirements
before the preparation of construction plans and specifications
could begin in the fall of 1976. The construction contract
for the treatment facility was awarded in the fall of
1977.
The construction phase of this project encompassed
two of the stormiest winters in the areas history.
Yet, sewage was diverted from the former treatment plant
to the Towns new facility on March 3, 1980 - seven
months before the contract completion date. North Attleboroughs
4.6 mgd water pollution control facility was designed
to treat all wastewater from the Town of North Attleborough
and neighboring Town of Plainville until approximately
the year 2000, thus helping to stimulate substantial
industrial and residential development in the area.
A regional interceptor was also constructed as part
of this project, which conveys wastewater from PlainviIle
to the treatment plant and eliminated the routine overflowing
of the old interceptor.
This $17,500,000 program was funded by grants of $12.5
million from the Federal Government and $2.5 million
from the Massachusetts Division of Water Pollution Control.
North Attleboroughs share of the total project
cost was $1.6 million. As a joint user of the facility,
the Town of Plainville also contributed $.6 million
for its share of the facility.
For the past thirty years North Attleborough has worked
to formulate a cost effective and environmentally sound
program for wastewater collection and treatment. As
a result the Town now has a water pollution control
facility, which has abated ongoing degradation of the
areas water quality, improved the aesthetic value
of the Ten-Mile River and protected the public and environmental
health of the community. Completion of this water pollution
control facility has made the Towns sewage treatment
system available to additional areas of the Town through
extensions of the sewage collection system.
As required by a federal mandate, in the early 1980's,
the Town began to study the effects of local industrial
wastes. This study determined the character of these
wastes, assessed their relative compatibility with the
sewerage system, and established industrial pretreatment
regulations for all incompatible wastes. As a result
of this study the Industrial Pretreatment Division was
created. Today, this function is overseen by an Industrial
Pretreatment Coordinator who regulates the industrial
and commercial waste in Town.
In June 1989 the Town of North Attleborough reached
another major milestone in its ongoing sewer extension
program with the completion of the East Side Interceptor
and Patrick P. Grimaldi Pumping Station. A $1,700,000
grant from the U.S. Environmental Protection Agency
and a matching $2,670,000 grant from the Massachusetts
Division of Water Pollution Control funded the interceptor
and pumping station projects.
The Waste Water Treatment Facility that was completed
in 1980 was designed as an advanced wastewater treatment
plant using treatment processes understood at that time
that were capable of meeting what was considered to
be stringent effluent limitations.
Treatment facilities at the plant include screening,
aerated grit chambers, primary clarifiers, first-stage
aeration tanks and clarifiers, second-stage aeration
tanks and clarifiers, gravity sand filters, chlorine
contact tanks, dechlorination facilities, and post aeration
tanks. Sludge handling facilities include flotation
thickeners and centrifuges.
Flow to the facility includes wastewater from two influent
sewers and septage. The headwork's of the facility provides
screening, grit removal, commutation and chemical addition
for phosphorous removal in the primary clarifiers. Two-stage
mechanical aeration provides for biological treatment
of Biochemical Oxygen Demand (BOD) and nitrogenous wastes.
The gravity sand filters provide final polishing of
the effluent. Chlorine is injected into the effluent
to destroy pathogens. The effluent is then de-chlorinated
to eliminate any chlorine by products that could have
a toxic effect on organisms that inhabit the river.
The post aeration tank is provided to maintain adequate
dissolved oxygen levels in the effluent to support aquatic
life in the river. Sludge handling is accomplished by
thickening the sludge to approximately 5% solids and
is then trucked off site for further treatment and disposal.
There are four publicity owned pump stations in the
wastewater collection system and one privately owned:
- The Patrick P.Grimaldi Pump Station
- The Industrial Park Pump Station
- The Falls Pump Station
- The Metcalf Road Pump Station
- The Norton Rd. (privately owned)
In addition to the pump stations, the collection system
has two metering stations; the Plainville metering station
at Kelly Blvd. and the Moran Street meter.
Wastewater Equipment Replacement Schedule:
As mentioned previously, the WWTF was designed for
a 15-20 year life cycle. The "Industry Standard"
service life for equipment that operates in a wastewater
treatment facility environment is 15-20 years. Through
an aggressive maintenance program the original equipment
installed in 1980 is still operating beyond its expected
service life. However, proper scheduled replacement
of equipment is critical to the continued uninterrupted
operations of the facility.
The Town has recently funded several equipment replacement
projects at the facility. They include:
- Replacement of Sludge Thickening equipment
- Replacement of Mechanical Bar Screen
- Replacement of Channel Grinder
- Replacement of Four Blowers for the Grit Chamber
and Sludge Holding Tank
- Replacement of Make Up Air Units
- Rehabilitation of the First Stage Pump Station
- Rehabilitation of the Second Stage Pump Station
- Partial rehabilitation of the Sand Filter Building
In order to properly treat the effluent flows into
the Ten-Mile River and protect the environment it is
crucial that the following replacement schedule be adhered
to. Waiting for equipment to breakdown before it is
replaced is not an effective way to manage this important
facility. An equipment replacement program is included
on the following pages.

TECHNOLOGY REPLACEMENT PROGRAM
The Department relies heavily on information technology
for day to day functioning, customer service and overall
management of the DPW. Staff utilizes desktop computers,
printers, scanners and laptops. In order to stay current
with technological advances, the Department has developed
a computer replacement program.
The Department's philosophy with regard to the standard
PC is driven by the following two (2) principles:
- Buy the least expensive PC that meets the current
software needs. This approach reduces the functional
life expectancy while offering a more attractive price.
- Buy the latest and most powerful technology available
to extend the functional life expectancy of the investment.
This approach extends the life of the equipment but
requires paying premium prices for the latest and
fastest technology.
The Public Works Department attempts to balance these
two principles with respect to all personal computer
purchases. Technology is advancing so rapidly that a
new generation of personal computer comes to market
every eighteen months or sooner. At this accelerated
pace, the standard PC configuration may change several
times during the course of a year. By setting a standard
somewhere in the middle, the Department is not paying
a premium on the latest technology and yet there is
a reasonable life expectancy for the purchased equipment.
Allocation/Reallocation of Hardware
Each Division within the Department has different hardware
needs. Some applications require more powerful computers
than others. For example, a user that only requires
word processing capabilities does not need as much computing
resource as a user that is using a mapping program or
desktop publishing. Computer resources are allocated
based on the type of application that is being used
by that Division.
It has been common practice to move hardware where
it is most appropriate to the task. If a division has
a need to upgrade their hardware because of newer applications
requiring more computer resources, that particular hardware
may be reallocated within the department where it can
be appropriately used for other tasks that may not require
as much computing resources.
ROADWAYS
Maintenance of Roads:
North Attleborough has a total of 122.6 road
miles. Of the total mileage:
- 97.12 miles have bituminous concrete surfaces
- 10.41 miles are composite roadways
- 9.54 miles are surface treated roadways
- 5.53 miles are gravel roadways.
In 1997 the Board of Public Works contracted with Vanasse
Hangen Brustlin, Inc. (VHB) to develop a roadway management
program for the Towns roadways. This roadway management
study describes existing conditions of the roadways
and develops a procedure to collect, organize, and maintain
a complete roadway database. The data can then be used
for keeping a historical record of the Towns infrastructure,
and for managing and evaluating existing and projected
road conditions.
This ongoing effort will establish and perpetuate a
roadway management program that will properly forecast
budget requirements. This will allow the Department
of Public Works to effectively maintain the roadway
network owned by the Town.
Roadway Management System Methodology:
VHB collected information such as the roadway length,
width, and classification, and then divided the roadways
into segments to create a base map of items that seldom
change. The next step was to evaluate the condition
of the pavement by recording distresses such as potholes,
alligator cracking, structural cracking, drainage issues,
and pavement distortions and then ranking the severity
of each condition. A Pavement Condition Index (PCI)
was generated for each surfaced, public roadway segment
using the distress data collected. PCI is measured on
a scale from zero to one hundred, with zero describing
a road in extremely poor condition and one hundred representing
a pavement in excellent condition. The zero to one hundred
scale is divided into five treatment bands in order
to categorize the types of repair needed.
The treatment bands are as follows:
PCI Rating Action Needed
PCI #1 (0-60) Reconstruction - poor condition, base
repairs needed
PCI #2 (61-72) Structural Improvement - fair condition
pavement, surface structure needs added strength for
existing traffic.
PCI #3 (73-85) Preventative Maintenance - good condition,
may need crack sealing, localized improvements, and
surface sealing
PCI #4 (86-92) Routine Maintenance - very good condition,
may need crack sealing or localized repairs.
PCI #5 (93-100) Do Nothing - excellent, no repairs
necessary at this time.
The pavement management system was used to propose
various budget scenarios, based on road inventory and
pavement distress information, to evaluate whether the
overall road system would improve, stabilize or deteriorate
at alternative funding levels. The pavement maintenance
budget alternatives project different future investment
levels, based on sound pavement management practice,
and prudent spending of available dollars. The budgeting
process uses a benefit value prioritization to calculate
the funds needed to achieve desired roadway conditions.
The benefit value formula is calculated using variables
representing traffic volume, repair service life, road
segment length, PCI, and costs. Without considering
the regulatory signs, signals, drainage, curbing, or
sidewalks, but simply the road surface, it would cost
at least $ 67 million in today's dollars to replace
the existing roadway infrastructure.
Reconstruction of Roads
Strategy:
The roads in the "Reconstruction" category
have deteriorated to the point where basic maintenance
work is an ineffective solution and where the base must
be strengthened. Work will include replacement of base
materials, grinding of road surfaces, installation of
under drains, adjustment of utility structures and full
depth pavement. There are 6.59 miles of roads
in the community that need to be reconstructed.
As previously indicated, the strategy of the Department
is to allocate the vast majority of its existing roadway
maintenance funds to the "annual maintenance"
category. This approach, however, expends all of the
present funding provided annually by the Town ($100,000.00)
and all Chapter 90 funds provided by the State ($550,000.00).
Thus, the Department will request additional funds to
reconstruct roads throughout the community that have
a PCI of 60 or under.
SIDEWALK REPAIR
Background
In 1997 the Board of Public Works contracted
with Vanasse Hangen Brustlin, Inc. (VHB) to develop
a roadway management program for the Town. All of the
roads and sidewalks were studied in this effort. The
roadway management study describes existing conditions
for sidewalks and rates the sidewalks in four categories:
Excellent, Good, Fair and Poor condition. There are
approximately 49.32 miles of sidewalks in the
Town of North Attleboro. The description of the rating
categories and the results of the study are detailed
next.
Sidewalk Information:
Rating
Length % of Total
Comments
Excellent- 11.49 miles
23% No defects
Good -
6.17 miles
13% Few deficiencies
(deficiencies include: ruts, uneven surfaces, some cracking)
Fair -
30.56 miles 62%
Large cracks, spauling, heaves/settlement less than
one inch
Poor -
1.1 miles
2%
Major cracks, heaves/settlement more that one inch,
depressions
Repair Schedule
As mentioned, there are an estimated
49 Miles of sidewalks in North Attleborough (39 miles
of asphalt, 10 miles of concrete). There are 1.1
miles of sidewalk in poor condition. These sidewalks
should be repaired as quickly as possible to prevent
tripping hazards for pedestrians. The cost estimate
to repair the 1.1 miles of sidewalk in poor condition
is approximately $150,000.00.
Repair materials
Sidewalks in the Town of North Attleborough
are constructed of two different kinds of sidewalk materials;
concrete and asphalt. To ensure uniform appearance of
the sidewalks throughout the community, sidewalk materials
will be specified as per the Planning Board Rules
and Regulations Governing Subdivision of Land.

SEWER COLLECTIONS
SYSTEM
The Town of North Attleborough's Sanitary Sewer Collection
System consists of approximately 57 miles of sewer
pipes, manholes, and appurtenances, which flow down to
the Wastewater Treatment Facility.
The collection system's first pipes
were installed in 1910. The system currently is comprised
of six different types of pipe with varying sizes and
service life. The service life of sewer pipes is determined
by the structural integrity of the pipe, materials and
the connections that join them. The pipe material used
in North Attleboro and its anticipated service life
are as follows:
|
PVC - Polyvinyl Chloride
|
21.65 miles
|
100 Years
|
|
VC - Vitrified Clay
|
23.36 miles
|
50 Years
|
|
AC - Asbestos Concrete
|
5.58 miles
|
60 Years
|
|
CICL - Ductile Iron Cement Lined
|
2.63 miles
|
75 Years
|
|
RCP - Reinforced Concrete Pipe
|
3.17 miles
|
80 Years
|
|
FM - Forced Main
|
.27 miles
|
100 Years
|
|
Total
|
56.66 miles
|
|
Collection System Operation &
Maintenance
Although most people associate proper
operation and maintenance (O&M) with wastewater
pump stations, other components of the wastewater collection
system also require continuous O&M. Comprehensive
O&M is necessary to ensure that the collection system
reliably transports wastewater from individual users
to the treatment facility. A successful O&M program
for a wastewater collection system provides many benefits
including:
- Elimination of backups/overflows and associated
public health hazards
- Utilization of the full hydraulic capacity of the
system
- Extended service life and protection of capital
investment in the collection system
- Reduced operating and capital costs
- Safer work environment resulting in fewer accidents
and compensation claims
- Minimized damage to public/private property associated
claims and liability
Visual Inspection and Cleaning
Visual inspection and cleaning of the
collection system should be performed on a routine basis,
not just in response to complaints or blockages. The
necessary frequency will vary significantly depending
on the age and condition of the system components, but
should be often enough to locate and remove obstructions
before complete blockages occur, which will help eliminate
backups, overflows, and property damage. Over time,
experience and proper record keeping will indicate problem
areas where blockages occur most often. These areas
should be inspected and cleaned more frequently than
other areas. Other areas within the collection system
that require more frequent cleaning include:
- Siphons and associated tributary lines
- Lines at minimum slope and scouring velocities
- Areas where bottlenecks or frequent surcharging
occur
In an effort to ensure that all of
the lines are routinely cleaned within a reasonable
period of time, a portion of the system should be cleaned
each year, with the goal of cleaning the entire system
every five to ten years. For North Attleborough, a goal
of 75,000 linear feet per year is recommended.
Manhole Inspection
Every manhole that is opened and used
for routine cleaning should be inspected. Following
this general rule will ensure that all manholes within
the system are inspected every five to ten years.
TV Inspection
We strongly recommend internal inspection
of the collection system via close circuit television.
This is accomplished by using a sewer "camera truck".
TV inspection provides a continuous view of lengths
of pipe up to 1,000 feet that are otherwise inaccessible.
This method provides for identification of sources of
infiltration, inflow, root intrusion, structural defects,
and poor joint condition. Since sewer lines should be
cleaned prior to TV inspection, routine cleaning and
TV inspection should be coordinated to avoid the duplication
of efforts. Under ideal conditions, routine cleaning
should be followed by routine TV inspection.
Siphons
Siphons must be inspected and maintained
on a regular basis to ensure proper operation. The town
has two siphons, which are located on Mt. Hope street
and North Avenue. The frequency of required inspection
for siphons depend on a variety of factors, including:
- The size and design of the siphon and the surrounding
pipes
- The amount and velocity of flow passing through
the siphon
- The amount and type of debris in the wastewater(i.e.,
large quantities of sand or grease)
In general, siphons should be inspected
once a week to ensure that they are functioning properly.
The key to maintaining a siphon is to maintain the sewer
lines in the tributary area. By ensuring that debris
is regularly removed from all of the sewer lines that
flow into the siphon, accumulation of debris within
the siphon can be minimized.
Easements
In North Attleboro a small percentage
of the collection system is located within cross-country
easements. Ideally, cross-country easements should be
maintained as soon as they are constructed. Maintenance
should include, at a minimum, ensuring that the easement
boundaries remain clearly marked; keeping the easement
property from becoming overgrown with trees and brush;
and performing routine sewer line cleaning, manhole
inspection, and TV inspection.
Some of easements in Town are overgrown,
preventing access to manhole and sewer lines. A program
to reclaim the easements should be developed and implemented.
This program should include the following basic steps:
- Surveying. Easements must be surveyed to
determine the legal boundaries since the sewer line
was not necessarily constructed down the middle of
the easement.
- Clearing. Easements must be cleared of trees,
brush, and other plants, as well as fences and other
man-made obstacles that may have been put within the
legal easement boundaries.
- Locating manholes. All manholes along easements
must be located and documented. Documenting the location
of manholes through the use of a Global Positioning
System (GPS) device is highly recommended.
- Cleaning and Inspecting. Sewer lines within
the easements should be cleaned and TV inspection
performed.
- Performing Maintenance. Once reclaimed,
easements should be properly maintained.
WATER SUPPLY
AND WATER DISTRIBUTION SYSTEM
The Town of North Attleborough has nine
groundwater supply sources, seven of which are located
in the Ten Mile River Basin while two are located in
the Blackstone River Basin. Together they provide 7.8
million gallons per day safe yield. The water distribution
system consists of approximately 110 miles of water
mains ranging in diameter from four to sixteen inches.
In October of 1998, Tata & Howard
Engineers Inc., completed a comprehensive study of North
Attleborough's water distribution system. The recommendations
contained in this report were based on computer simulations
of the existing water distribution system, and predicted
future water supply and system demands. The parameters
governing the study were based on the data supplied
by the DPW, consultant participation, Insurance Services
Office (ISO), and input from the Fire Chief.
The Water Supply and Distribution System
were evaluated in each of the following categories.
- Provide 35 pounds per square inch (psi) of pressure
during peak hour demands.
- Provide estimated fire flow requirements during
maximum day demand conditions. In general, the flows
required for proper fire protection are based on maintaining
a residual pressure of 20 psi.
-
Water Supply and Treatment:
This is an area where there are no immediate projects
that must be implemented. The two projects listed,
additional groundwater supply at the Adamsdale Wellfield
and Hillman Wellfield will not have to be funded
for quite some time. Once completed however, these
improvements will help to insure that the growing
population of the Town will be adequately supplied
with quality water in the future.
-
Water Quality: These improvements
address areas such as hydrant flushing of the mains
twice a year, an on-going water meter replacement
program, valve and hydrant replacement program along
with the replacement of old water mains. The water
mains are constructed of various materials including
cast iron (CI), cement lined ductile iron (CLDI),
asbestos cement (AC), trancite (TR), and polyvinyl
chloride (PVC). The material that the mains are
constructed of can influence the Town's water quality.
The following is the expected service life of water
mains based on water quality assumptions for the
different materials mentioned.
|
CI
|
50 years
|
|
CLDI
|
100 years
|
|
TR
|
100 years
|
|
PVC
|
100 years
|
Construction of the Town's water distribution
system began in 1884 with cast iron mains. All mains
installed up to 1944 were cast iron. In 1944 trancite
mains were introduced and in 1966 ductile iron mains
and cement lined ductile mains were also installed.
Cast iron mains continued to be installed until 1984
and are the most problematic with respect to tuberculation
build up and reduced flow capacity. A program to replace
these old mains to improve water quality will be specified
in the near future.
Comprehensive Wastewater Management
Plan (CWMP):
In 1981, the Town constructed an Advanced Wastewater
Treatment Facility that is located in Attleboro Falls.
Since that time the Town has continued to expand its
sanitary sewer collection system to meet the demands
for its growing residential and commercial population.
A Town-wide master plan for the collection system and
treatment facilities known as the "Facility Plan"
was developed and completed in 1984. The Facility Plan
by Whitman & Howard, Inc. identified the unsewered
areas of Town and determined the best routes by which
to sewer these areas in the future. This Plan has been
used as a guide for the Town when residents and developers
approach the Board of Public Works with an interest
in extending a sewer line.
Due to major residential and commercial growth in the
Town along with the revised State Environmental Code,
Title 5, the needs portion of the Facility Plan has
become outdated. The Board of Public Works decided that
it was necessary to update its Facility Plan to incorporate
a re-survey of the unsewered areas of Town and re-establish
a comprehensive Town-wide sewer extension plan for the
next 20 years based on the needs of the different areas.
This new plan is called the Comprehensive Wastewater
Management Plan (CWMP) and was completed in mid-1999.
The CWMP divided the unsewered areas of Town into 20
Sub-Areas to determine priority needs and also looked
at small pockets of unsewered areas within the Central
and Falls areas of Town. These small pockets are called
"sewer extensions".
In order for the Town to be eligible for low interest
State loans for new sewer construction, the State specified
the following criteria, which are to be used in determining
new sewers.
These areas were evaluated based on several criteria:
- Imminent septic system failure
- Septic system within Zone I public drinking water
well
- Septic systems located on lots smaller than one-quarter
acre
- Septic systems greater than 20 years in age
- Severe soil limitations
- Septic systems located on lots smaller than one-half
acre but greater than one-quarter acre in size
- Health/water quality issues with septic systems
within 50 feet of a surface water body
- Septic system located in 100 year flood plain
- Septic systems located within a Interim Wellhead
Protection Area
- Septic system located Zone II aquifer recharge area
- Moderate soil limitations
In addition a questionnaire was mailed to over 3,000
residences not currently on the Town sewer system to
obtain their input on the situation. Also, alternative
solutions were evaluated to providing centralized sewer
disposal in these areas.
Total
Areas Time Frame to Complete Estimated Cost Projected
Annual Expenditures to Complete Project
Group A 2000-2008 $ 21,500,000 $ 2,625,000
Group B 2008-2015 $ 26,000,000 $ 3,250,000
Group C 2020
Policy for new sewers in Group B and Group C:
It is recognized that development may occur in areas
listed in Group B and Group C. Since the Town does not
plan to sewer locations listed in Group B and Group
C areas for several years, proponents desiring to install
new sewers in these areas must design sewers to the
capacity, specifications and features as specified by
the Board of Public Works. Additionally, gravity sewers
will be the optimum approach for these new sewers. Proponents
shall be responsible for all costs associated with conducting
capacity analysis for the internal network of sewer
pipes affected by the proposed project as well as determining
the impacts on the wastewater treatment facility associated
with any new sewers in the Group B and Group C areas.

|